The Public-Records LedgerCity of London, Ontario · Final Public Edition 5.0
Projects

Eight capital, project and fund dossiers

Evidence lock: August 20, 2026

Each dossier is a named project or fund with a public dollar figure attached to it somewhere in the record. The “Unresolved test” column is the specific, single thing standing between that public figure and a transaction-level conclusion — never translate an unresolved test into a finding.

Eight named capital, project and fund dossiers
1 · Highbury Facility rebuildLTC / capital service improvementCity project book: $301.9M; LTC phase figures imply about $321.7MTwo public budget vintages do not reconcile. 2025 LTC report says $5.0M did not get underway and carried to 2026.Budget-vintage and delivery reconciliationR1
2 · Roadmap to 3,000Housing ServicesProject book: $78.0M2025 development report tracks 2,576 City-funded affordable units: 675 in progress, 1,360 in planning; stage for the balance is not stated in the summary.Cost per completed/occupied affordable unitR4
3 · Fanshawe campus grantEconomic developmentProject GG1721-6: $20.75MNamed in the service-improvement capital book; end-to-end grant payment and outcome closeout not reproduced.Agreement, payments, milestones, closeoutR1R6
4 · Mud Creek Phase 2BStormwaterTotal budget $24.720M; 2025 financing/spend lines reproducedEA approved 2017; site work began 2025; construction continues into 2026. Award, change orders and physical completion not joined publicly.Award, amendments, FAC, percent completeR1R2
5 · Springbank DamEnvironment / river projectStage 1 estimate $14.6M; decommissioning budget up to $3MPublic record explains estimate changes, but final decommissioning cost and closeout were not located.Final cost and closeout certificateR1
6 · Wharncliffe/HortonTransportation$90M estimate; $39.6M funding gap reported Jan. 2026Unfunded at construction scale; no procurement expected yet. A smaller Wharncliffe line in the DC report is not the same project.Updated estimate, financing plan, scheduleR1
7 · Operating contingency reserveCorporate finance2018 balance $35.18M vs $96.59M policy target; 2024 audited contingency line $109.8MTwo accounting presentations are not proven to be the identical fund. Reconciliation is required before claiming recovery.Fund mapping and policy-target calculationR6
8 · Highway 401 / Highway 4Provincial transportationNo City capital cost establishedMTO project; City endorsed municipal road closures. This lead is not a City-spending finding as framed.None unless a different 401-adjacent project is specifiedClosed — no further test